Tuesday, August 30, 2016

Site Visit

Contractor was breaking up and hauling off old bridge today. they had installed the creek crossing as well.





i talked with contractor and he told me it would be a couple weeks before they will be ready to start driving piling. just a two man crew at this time.

Monday, August 15, 2016

Site Visit

Surveyors were staking out road and bridge with offsets. contractor arrived shortly after.
















Foreman and one helper are going to start laying out bents for bridge. cant take old bridge out until DNR permit.