Tuesday, September 27, 2016

Site visit-Pour Bent 1 Cap

 Contractor was finishing up form work for Bent 1 cap, Concrete arrived and i tested it. Slump: 4", Air: 6.0%, Temp:85°. made three cylinders.
 Bent 2 after forms had been removed.


 Pour went good


 putting the final touches to the concrete.


Wednesday, September 21, 2016

Site Visit-Bent 2 Cap Pour

 Contractor was ready to Pour Bent 2 Cap, I checked the steel placement and form work. Concrete was on site at 1:47pm, I tested concrete. Slump: 41/2", Air: 6%, Temp: 80°. I made 3 cylinders, pour went good.









Contractor will try pouring Bent 1 Cap on Friday.

Monday, September 19, 2016

Site visit-Seat Piling for Bents 1 & 2

 I arrived onsite at 7:45, crew showed up at 8:05. Moved equipment into area to start seating piling for Bent 2






 Finished driving piling for Bent 2, moved hammer and crane to other side to drive Bent 1
Finished driving all piling around 11:00, checked with contractor about schedule and headed back