Contractor was finishing up form work for Bent 1 cap, Concrete arrived and i tested it. Slump: 4", Air: 6.0%, Temp:85°. made three cylinders.
Bent 2 after forms had been removed.
Pour went good
putting the final touches to the concrete.
Tuesday, September 27, 2016
Wednesday, September 21, 2016
Site Visit-Bent 2 Cap Pour
Contractor was ready to Pour Bent 2 Cap, I checked the steel placement and form work. Concrete was on site at 1:47pm, I tested concrete. Slump: 41/2", Air: 6%, Temp: 80°. I made 3 cylinders, pour went good.
Contractor will try pouring Bent 1 Cap on Friday.
Contractor will try pouring Bent 1 Cap on Friday.
Monday, September 19, 2016
Site visit-Seat Piling for Bents 1 & 2
I arrived onsite at 7:45, crew showed up at 8:05. Moved equipment into area to start seating piling for Bent 2
Finished driving piling for Bent 2, moved hammer and crane to other side to drive Bent 1
Finished driving all piling around 11:00, checked with contractor about schedule and headed back
Finished driving piling for Bent 2, moved hammer and crane to other side to drive Bent 1
Finished driving all piling around 11:00, checked with contractor about schedule and headed back