Monday, November 28, 2016

11-17-2016 erosion control and seeding


Set silk sock on the South West side of the bridge for erosion control prior to spraying seed and mulch.


Set the silk sock on the South East side of the bridge for erosion control prior to spraying seed and mulch.


Silk sock added to the South East side of bridge just above the rip rap.


Crew spraying seed and mulch on the East bridge approach.



Setting the silk sock for erosion control, on the North East side on the bridge project.




Placing silk sock for erosion control on the North West side of the bridge.

Wednesday, November 16, 2016

Site visit with Contractor

 Contractor was ready to walk through site, site was in good shape. there was a couple thing that i ask him to address, the roadway had a couple pot holes that needed fixed and the other was silt sock. Contractor informed me that the seeding and erosion will be installed on Thursday the 17th.













 Contractor is going to grade the road one more time before removing equipment.



















Monday, October 31, 2016

Site Visit, Check roadway compaction

 Contractor was ready to roll the roadway surface, I watched the loaded truck and found no soft spots.